Revision: October 20052005 QX56
Ambient Sensor CircuitEJS003Y2
COMPONENT DESCRIPTION
Ambient Sensor
The ambient sensor is attached on the radiator core support (left
side). It detects ambient temperature and converts it into a value
which is then input into the front air control.
AMBIENT TEMPERATURE INPUT PROCESS
The front air control includes a processing circuit for the ambient sensor input. However, when the tempera-
ture detected by the ambient sensor increases quickly, the processing circuit retards the front air control func-
tion. It only allows the front air control to recognize an ambient temperature increase of 0.33°C (0.6°F) per 100
seconds.
This prevents constant adjustments due to momentary conditions, such as stopping after high speed driving.
Although the actual ambient temperature has not changed, the temperature detected by the ambient sensor
will increase. This is because the heat from the engine compartment can radiate to the front grille area, loca-
tion of the ambient sensor.
DIAGNOSTIC PROCEDURE FOR AMBIENT SENSOR
SYMPTOM: Ambient sensor circuit is open or shorted. Using the
CONSULT-II, DTC B257B or B257C is displayed. Without a CON-
SULT-II, code 40 or 41 is indicated on front air control as a result of
conducting the front air control self-diagnosis.
1. CHECK VOLTAGE BETWEEN AMBIENT SENSOR AND GROUND
1. Disconnect ambient sensor connector.
2. Turn ignition switch ON.
3. Check voltage between ambient sensor harness connector E1
terminal 1 (P) and ground.
OK or NG
OK >> GO TO 2.
NG >> GO TO 4.
WJIA0562E
WJIA0456E
1 - Ground : Approx. 5V
WJIA1971E
ATC-158
HEATER & COOLING UNIT ASSEMBLY
Revision: October 20052005 QX56
7. Move the two front seats to the rearmost position on the seat track.
8. Remove the instrument panel and console panel. Refer to IP-10, "
INSTRUMENT PANEL ASSEMBLY" .
9. Remove the steering column. Refer to PS-10, "
STEERING COLUMN" .
10. Disconnect the instrument panel wire harness at the RH and LH in-line connector brackets, and the fuse
block (J/B) electrical connectors. Refer to PG-4, "
POWER SUPPLY ROUTING CIRCUIT" .
11. Disconnect the steering member from each side of the vehicle body.
12. Remove the front heater and cooling unit assembly with it attached to the steering member, from the vehi-
cle.
CAUTION:
Use care not to damage the seats and interior trim panels when removing the front heater and
cooling unit assembly with it attached to the steering member.
13. Remove the front heater and cooling unit assembly from the steering member.
Installation
Installation is in the reverse order of removal.
CAUTION:
Replace the O-ring of the low-pressure pipe and high-pressure pipe with a new one, and apply
compressor oil to it when installing it.
After charging the refrigerant, check for leaks.
NOTE:
Fill the engine cooling system with the specified coolant mixture. Refer to MA-14, "REFILLING ENGINE
COOLANT" .
Recharge the A/C system. Refer to ATC-175, "Evacuating System and Charging Refrigerant" .
REAR HEATER AND COOLING UNIT ASSEMBLY
Removal
1. Discharge the refrigerant from the A/C system. Refer to ATC-175, "Discharging Refrigerant" .
2. Drain the coolant from the engine cooling system. Refer to MA-13, "
DRAINING ENGINE COOLANT" .
3. Disconnect the rear heater core hoses from the rear heater core.
4. Disconnect the rear A/C pipes from the rear expansion valve.
5. Remove the rear RH interior trim panel. Refer to EI-35, "
BODY
SIDE TRIM" .
6. Disconnect the following electrical connectors:
Rear blower motor
Rear blower motor resistor
Rear air mix door motor
7. Disconnect the ducts from the rear heater and cooling unit
assembly.
8. Remove the rear heater and cooling unit assembly.
Installation
Installation is in the reverse order of removal.
CAUTION:
Replace the O-ring of the low-pressure pipe and high-pressure pipe with a new one, and apply
compressor oil to it when installing it.
After charging the refrigerant, check for leaks.
NOTE:
Fill the engine cooling system with the specified coolant mixture. Refer to MA-14, "REFILLING ENGINE
COOLANT" .
Recharge the A/C system. Refer to ATC-175, "Evacuating System and Charging Refrigerant" .
Removal and Installation for Rear Heater Core PipesEJS00536
REMOVAL
1. Drain the coolant from the engine cooling system. Refer to CO-10, "DRAINING ENGINE COOLANT" .
2. Remove the upper and lower luggage RH side finisher. Refer to EI-35, "
BODY SIDE TRIM"
LJIA0021E
ATC-182
REFRIGERANT LINES
Revision: October 20052005 QX56
2. Install the magnet coil harness clip using a screwdriver.
3. Install the pulley assembly using Tool and a wrench, then install
the snap ring using snap ring pliers.
4. Install the clutch disc on the compressor shaft, together with the
original shim(s). Press the clutch disc down by hand.
5. Install the clutch pulley bolt using Tool, to prevent the clutch disc
from turning and tighten the bolt to specification.
CAUTION:
After tightening the clutch pulley bolt, check that the clutch
pulley rotates smoothly.
6. Check the pulley clearance all the way around the clutch disc as
shown.
7. If the specified clearance is not obtained, replace the adjusting
spacer to readjust.
8. Connect the compressor electrical connector.
9. Install the drive belt. Refer to EM-12, "
DRIVE BELTS" .
10. Install the engine under cover and the splash shield.Tool number : — (J-38873-A)
WJIA1016E
WHA184
Tool number : J-44614
WHA229
Clutch disc-to-pulley clearance : 0.3 - 0.6 mm
(0.012 - 0.024 in)
WHA194
REFRIGERANT LINES
ATC-183
C
D
E
F
G
H
I
K
L
MA
B
AT C
Revision: October 20052005 QX56
BREAK-IN OPERATION
When replacing compressor clutch assembly, always conduct the break-in operation. This is done by engag-
ing and disengaging the clutch about 30 times. Break-in operation raises the level of transmitted torque.
Removal and Installation for Low-pressure Flexible HoseEJS003YV
REMOVAL
1. Remove the engine room cover using power tools.
2. Remove the engine air cleaner and air ducts. Refer to EM-14, "
AIR CLEANER AND AIR DUCT"
3. Remove the cowl top extension. Refer to EI-18, "COWL TOP" .
4. Discharge the refrigerant. Refer to ATC-175, "
HFC-134a (R-134a) Service Procedure" .
CAUTION:
Cap or wrap the joint of the pipe with suitable material such as vinyl tape to avoid the entry of air.
5. Remove the low-pressure flexible hose.
INSTALLATION
Installation is in the reverse order of removal.
Refer to ATC-177, "
Components" .
CAUTION:
Replace the O-ring of the low-pressure flexible hose with a new one, then apply compressor oil to
it when installing it.
After charging refrigerant, check for leaks.
Removal and Installation for High-pressure Flexible HoseEJS003YW
REMOVAL
1. Remove the engine under cover.
2. Remove the engine air cleaner and air ducts. Refer to EM-14, "
AIR CLEANER AND AIR DUCT" .
3. Discharge the refrigerant. Refer to ATC-175, "
HFC-134a (R-134a) Service Procedure" .
4. Remove the high-pressure flexible hose.
CAUTION:
Cap or wrap the joint of the pipe with suitable material such as vinyl tape to avoid the entry of air.
INSTALLATION
Installation is in the reverse order of removal.
Refer to ATC-177, "
Components" .
CAUTION:
Replace the O-ring of the high-pressure flexible hose with a new one, then apply compressor oil to
it when installing it.
After charging refrigerant, check for leaks.
Removal and Installation for High-pressure PipeEJS003YX
REMOVAL
1. Remove the cowl top extension. Refer to EI-18, "COWL TOP" .
2. Disconnect the battery negative cable.
3. Reposition the IPDM E/R aside.
4. Remove the front right wheel and tire assembly. Refer to WT-7, "
Rotation" .
5. Position aside the front floor insulator.
6. Discharge the refrigerant. Refer to ATC-175, "
HFC-134a (R-134a) Service Procedure" .
7. Remove the low pressure pipe. Refer to ATC-184, "
Removal and Installation for Low-pressure Pipe" .
8. Remove the high-pressure pipe.
CAUTION:
Cap or wrap the joint of the pipe with suitable material such as vinyl tape to avoid the entry of air.
INSTALLATION
Installation is in the reverse order of removal.
Refer to ATC-177, "
Components" .
ATC-184
REFRIGERANT LINES
Revision: October 20052005 QX56
CAUTION:
Replace the O-ring of the high-pressure pipe with a new one, then apply compressor oil to it when
installing it.
After charging refrigerant, check for leaks.
Removal and Installation for Low-pressure PipeEJS003YY
REMOVAL
1. Discharge the refrigerant. Refer to ATC-175, "HFC-134a (R-134a) Service Procedure" .
2. Remove the cowl top and the cowl top extension. Refer to EI-18, "
COWL TOP" .
3. Remove the low-pressure pipe.
CAUTION:
Cap or wrap the joint of the pipes with suitable material such as vinyl tape to avoid the entry of air.
INSTALLATION
Installation is in the reverse order of removal.
Refer to ATC-177, "
Components" .
CAUTION:
Replace the O-ring of the high/low-pressure pipe with a new one, then apply compressor oil to it
when installing it.
After charging refrigerant, check for leaks.
Removal and Installation for Underfloor Rear A/C PipesEJS00537
REMOVAL
1. Drain the coolant from the engine cooling system. Refer to CO-10, "DRAINING ENGINE COOLANT" .
2. Diconnect the negative battery terminal.
3. Discharge the refrigerant from the A/C system. Refer to ATC-175, "
HFC-134a (R-134a) Service Proce-
dure" .
4. Disconnect the chassis harness connector.
5. Set four suitable jacks at the body mounting points to support the vehicle body when it is seperated from
the frame.
6. Remove the RH body mount bolts. Refer to BL-159, "
Body Mounting"
7. Use the vehicle hoist to lower the frame from the body until there is sufficient clearance for the underfloor
rear high- and low-pressure A/C and heater core pipes from the body.
8. Remove the underfloor rear high- and low-pressure A/C and heater core pipes .
INSTALLATION
Installation is in the reverse order of removal.
Refer to ATC-177, "
Components" .
CAUTION:
Replace the O-rings of the high-pressure pipe and the high-pressure flexible hose with new ones,
then apply compressor oil to them after installing them.
After charging refrigerant, check for leaks.
Removal and Installation for Rear A/C PipesEJS00538
REMOVAL
1. Discharge the refrigerant from the A/C system. Refer to ATC-175, "HFC-134a (R-134a) Service Proce-
dure"
2. Remove the upper and lower luggage RH side finisher lower. Refer to EI-35, "BODY SIDE TRIM"
3. Disconnect the rear A/C pipes.
INSTALLATION
Installation is in the reverse order of removal.
Refer to ATC-177, "
Components" .
CAUTION:
Replace the O-rings of the high-pressure pipe and the high-pressure flexible hose with new ones,
then apply compressor oil to them after installing them.
After charging refrigerant, check for leaks.
ATC-190
REFRIGERANT LINES
Revision: October 20052005 QX56
2. Pour one bottle 7.4 cc (1/4 ounce) of the HFC-134a (R-134a) fluorescent leak detection dye (J-41447) into
the HFC-134a (R-134a) dye injector (J-41459).
CAUTION:
If repairing the A/C system or replacing a component, pour the HFC-134a (R-134a) fluorescent leak
detection dye (J-41447) directly into the open system connection and proceed with the service
procedures.
3. Connect the refrigerant dye injector (J-41459) to the low-pressure service valve.
4. Start the engine and switch the A/C system ON.
5. When the A/C system is operating (compressor running), inject one bottle 7.4 cc (1/4 ounce) of HFC-134a
(R-134a) fluorescent leak detection dye (J-41447) through the low-pressure service valve using HFC-
134a (R-134a) dye injector (J-41459). Refer to the manufacturer's operating instructions.
6. With the engine still running, disconnect the HFC-134a (R-134a) dye injector (J-41459) from the low-pres-
sure service valve.
7. Operate the A/C system for a minimum of 20 minutes to mix the HFC-134a (R-134a) fluorescent leak
detection dye (J-41447) with the A/C system oil. Depending on the leak size, operating conditions and
location of the leak, it may take from minutes to days for the HFC-134a (R-134a) fluorescent leak detec-
tion dye to penetrate an A/C system leak and become visible.
Electronic Refrigerant Leak DetectorEJS003Z8
PRECAUTIONS FOR HANDLING LEAK DETECTOR
NOTE:
When performing a refrigerant leak check, use a electronic refrigerant leak detector (J-41995) or equivalent.
Ensure that the electronic refrigerant leak detector (J-41995) is calibrated and set properly according to the
manufacturer's operating instructions.
The electronic refrigerant leak detector (J-41995) is a delicate
device. To use the leak detector properly, read the manufacturer's
operating instructions and perform any specified maintenance.
1. Position the probe approximately 5 mm (3/16 in) away from the
point to be checked as shown.
SHA1 96 FA
SHA707EA
REFRIGERANT LINES
ATC-191
C
D
E
F
G
H
I
K
L
MA
B
AT C
Revision: October 20052005 QX56
2. When checking for leaks, circle each fitting completely with the
probe as shown.
3. Move the probe along each component at a speed of approxi-
mately 25 - 50 mm (1 - 2 in)/second as shown.
CHECKING PROCEDURE
NOTE:
To prevent inaccurate or false readings, make sure there is no refrigerant vapor, shop chemicals, or cigarette
smoke in the vicinity of the vehicle. Perform the leak test in a calm area (low air/wind movement) so that the
leaking refrigerant is not dispersed.
1. Turn the engine OFF.
2. Connect the manifold gauge set (J-39183-C) to the A/C service ports. Refer to ATC-175, "
SETTING OF
SERVICE TOOLS AND EQUIPMENT" .
3. Check if the A/C refrigerant pressure is at least 345 kPa (3.52 kg/cm
2 , 50 psi) above a temperature of
16°C (61°F). If less than specification, recover/evacuate and recharge the system with the specified
amount of refrigerant. Refer to ATC-175, "
HFC-134a (R-134a) Service Procedure" .
NOTE:
At temperatures below 16°C (61°F), leaks may not be detected since the system may not reach 345 kPa
(3.52 kg/cm
2 , 50 psi) pressure.
4. Perform the leak test from the high-pressure side (front A/C compressor discharge “a” to evaporator inlet
“f” or rear piping connection “l”) to the low-pressure side (front A/C evaporator drain hose “g” to shaft seal
“k” and rear A/C evaporator drain hose “o” to piping connection “r”). Refer to ATC-177, "
Components" .
Clean the component to be checked and carefully move the electronic refrigerant leak detector probe
completely around the following connections and components.
Check the compressor shaft seal
Check the high and low-pressure pipe and hose fittings, relief valve, and compressor shaft seal
Check the liquid tank
Check the refrigerant pressure sensor
Check all around the service valves. Check that the service valve caps are screwed tightly on the ser-
vice valves (to prevent leaks).
NOTE:
After removing manifold gauge set (J-39183-C) from the service valves, wipe any residue from the ser-
vice valves to prevent any false readings by the electronic refrigerant leak detector (J-41995).
Evaporator
With engine OFF, turn blower fan on “High” for at least 15 seconds to dissipate any refrigerant trace in
the heater and cooling unit assembly. Wait a minimum of 10 minutes accumulation time (refer to the
manufacturer's recommended procedure for actual wait time) before inserting the electronic refrigerant
leak detector probe into the heater and cooling unit assembly drain hose.
SHA7 06 E
SHA708EA
ATC-192
REFRIGERANT LINES
Revision: October 20052005 QX56
NOTE:
Keep the probe inserted for at least 10 seconds. Use caution not to contaminate the probe tip with
water or dirt that may be in the drain hose.
5. If a leak is detected, verify at least once by blowing compressed air into the area of the suspected leak,
then repeat the leak check.
6. Do not stop when one leak is found. Continue to check for additional leaks at all system components and
connections.
7. If no leaks are found, perform steps 8 - 11.
8. Start the engine.
9. Set the heater A/C controls as follows:
NOTE:
For the automatic system, turn OFF the automatic controls and set the heater A/C controls manually.
a. A/C switch to ON
b. Air flow to VENT mode
c. Intake position to RECIRCULATION mode
d. Temperature to MAX cold
e. Blower speed to HIGH
10. Run the engine at 1,500 rpm for at least 2 minutes.
11. Turn the engine OFF and perform the leak check again following
steps 4 through 6 above.
Refrigerant leaks should be checked immediately after turning
the engine OFF. Begin with the leak detector at the compressor.
The pressure on the high pressure side will gradually drop after
the refrigerant circulation stops and pressure on the low pres-
sure side will gradually rise, as shown in the graph. Some leaks
are more easily detected when the pressure is high.
12. Before connecting the recovery/recycling recharging equipment to the vehicle, check the recovery/recy-
cling recharging equipment gauges. No refrigerant pressure should be displayed. If pressure is displayed,
recover the refrigerant from the equipment lines and then check the refrigerant purity.
13. Confirm refrigerant purity in supply tank using recovery/recycling recharging equipment and refrigerant
identifier equipment (J-41810-NI).
14. Confirm the refrigerant purity in the vehicle's A/C system using recovery/recycling recharging equipment
and refrigerant identifier equipment (J-41810-NI).
15. Discharge the A/C system using recovery/recycling recharging equipment. Repair the leaking fitting or
component as necessary.
16. Evacuate and recharge the A/C system and perform the leak test to confirm that there are no refrigerant
leaks.
17. Conduct the Operational Check to ensure system works properly. Refer to AT C - 5 7 , "
Operational Check
(Front)" and ATC-60, "Operational Check (Rear)" .
SHA8 39 E