GENERAL SPECIFICATION DATA
1
INFORMATION REV: 05/99 300Tdi ENGINE
Type Direct injection, turbocharged, intercooled.................................................................................
Number of cylinders 4.........................................................
Bore 90,47 mm.................................................................................
Stroke 97,00 mm...............................................................................
Capacity 2495 cc...........................................................................
Compression ratio 19.5:1±0.5:1 ............................................................
Valve operation O.H.V. pushrod operated................................................................
Crankshaft
Main bearing journal diameter 63,475 - 63,487 mm..........................................
Regrind dimensions 63,233 - 63,246 mm.........................................................
Crankpin journal diameter 58,725 - 58,744 mm................................................
Regrind dimensions 58,471 - 58,490 mm.........................................................
Crankshaft end thrust Taken on thrust washers at centre main bearing.......................................................
Crankshaft end float 0,05 - 0,15 mm.........................................................
Main bearings
Number and type 5 halved shells with oil grooves..............................................................
Diametrical clearance 0,0792 - 0,0307 mm.......................................................
Connecting rods
Length between centres 175,38 - 175,43 mm...................................................
Diametrical clearance (big-end bearings) 0,025 - 0,075 mm........................
End float on crankpin 0,15 - 0,356 mm.......................................................
Pistons
Type Aluminium alloy, combustion chamber in crown..................................................................................
Graphite coating on sidewalls.
Skirt diametrical clearance (at r/angle to gudgeon pin) 0,025 - 0,05 mm....
Maximum height above combustion face 0,8 mm.........................
Gudgeon pins
Type Fully floating.................................................................................
Fit in piston Hand push fit.......................................................................
Diameter 30,156 - 30,163 mm..........................................................................
Clearance in connecting rod 0,003 - 0,016 mm............................................
Piston rings
Type:
- Top Barrel edge, chrome plated........................................................................
- Second Taper faced..................................................................
- Oil control Expander and rails..............................................................
Gap in bore:
- Top 0,40 - 0,60 mm........................................................................
- Second 0,30 - 0,50 mm..................................................................
- Oil control 0,30 - 0,60 mm..............................................................
Clearance in piston grooves:
- Second 0,050 - 0,085 mm..................................................................
- Oil control 0,050 - 0,085 mm..............................................................
GENERAL SPECIFICATION DATA
3
INFORMATION FUEL SYSTEM
Fuel lift pump type Mechanical with hand primer............................................................
Fuel lift pump pressure 42 - 55 Kgf/cm
2(3 - 4 lbf/in2) at 1800 rpm .....................................................
Fuel filter Paper element in disposable canister..........................................................................
Air cleaner Paper element type........................................................................
COOLING SYSTEM
System type Pressurised, spill return, thermostatically controlled.....................................................................
water and anti freeze mixture. Pump assisted thermo
syphon. Coolant radiator combined with oil cooler and
turbo intercooler.
Cooling fan 11 blade axial flow 433 mm diameter, 1.29:1 drive.......................................................................
ratio, with viscous coupling.
Pump type Centrifugal, impellor, belt driven........................................................................
Thermostat opening 88°C .........................................................
Expansion tank cap pressure 1,06 Kgf/cm
2(15 Ibf/in2) (system pressure) ...........................................
CLUTCH
Type Valeo diaphragm spring.................................................................................
Centre plate diameter 235 mm.......................................................
Facing material Verto F202 grooved.................................................................
Release bearing Ball journal...............................................................
TRANSMISSION
Main gearbox
Type R380 Single helical constant mesh.......................................................................
Speeds 5 forward, 1 reverse, all synchromesh.............................................................................
Transfer box
Type LT230 Two speed reduction on main gearbox output. Front......................................................................
and rear drive permanently engaged via a lockable
differential
Rear axle
Type Spiral bevel, fully floating shafts.................................................................................
Ratio 3.54:1.................................................................................
ENGINE TUNING DATA
1
INFORMATION 300 Tdi ENGINE
Type2.5 Litre Turbo diesel intercooled .................................................................................
Firing order1-3-4-2 .....................................................................
Injection timing1,54 mm lift at T.D.C. ...............................................................
Injection timing with electronic EGR1,40 mm lift at T.D.C. ............................
Timing marks:
Valve timing - manual Slot for pin in flywheel and TDC mark on front pulley........................................................
Injection timing Timing pin (service tool).................................................................
Tappet clearances inlet and exhaust 0,20 mm cold...............................
Valve timing: Inlet Exhaust
- Opens 16°B.T.D.C. ............................................................................ 51°B.B.D.C.
- Closes 42°A.B.D.C. ............................................................................ 13°A.T.D.C.
- Peak 103°A.T.D.C. ............................................................................... 109°B.T.D.C.
- Lift 9,67 mm.................................................................................. 9,97 mm
Maximum governed speeds:
- No load (neutral/full throttle) 4600 + 40 - 120 rev/min...........................................
- Idle speed at running temperature 720±20 rev/min .................................
- Die-down time 4 seconds................................................................
INJECTION PUMP
Make & type - standard Bosch rotary R509 type with boost control and two....................................................
speed mechanical governor with auto advance and
solenoid electrical shut-off. Tamper proof sealing on,
no load governed speed and fuel adjustment screws.
Constant volume delivery valves
Make & type - Electronic EGR Bosch rotary R509/1 type with boost control and two.........................................
speed mechanical governor with auto advance and
solenoid electrical shut-off. Tamper proof sealing on
flight speed and fuel adjustment screws. Constant
volume delivery valves. Throttle position sensor for
EGR control.
HEATER PLUGS
Make & type Probe type, No.0100226129A Beru 12 volts.....................................................................
Time to reach operating temperature of 850°C 8 seconds...............
05ENGINE TUNING DATA
2
INFORMATION INJECTORS
Make & type - standard Bosch KBAL 90 P37....................................................
Nozzle type DSLA 145P366......................................................................
Opening pressure (working pressure) Initial pressure 200 atmospheres, Secondary 280..............................
atmospheres
TURBOCHARGER
Make & type Garrett T250 - 04.....................................................................
Maximum boost pressure 0,93 - 1,07 bar (13.5 - 15.5 lbf/in
2) measured at .................................................
wastegate actuator 'T' piece
MAINTENANCE
5
MAINTENANCE REV: 05/99 CHECK COOLING, INTERCOOLING AND HEATING
SYSTEMS
Check cooling, and heater systems for leaks and
pipes/hoses for security and condition. Refill or top up
as necessary.
CAUTION: It is important that the correct
procedure is followed when refilling or
topping up the cooling system to avoid
trapping air in the system.
WARNING: Do not remove caps and plugs
when engine is hot because cooling
system is pressurised and personal
scalding could result.
1.Remove plastic plugs from thermostat housing
and radiator.
2.Fill cooling system with correct concentration
and specification of anti-freeze.
See
LUBRICANTS, FLUIDS AND CAPACITIES,
Information, Recommended lubricants and
fluids
3.Fill from expansion tank until radiator is full, with
level in expansion tank the same as in radiator.
NOTE: Care should be taken to avoid
excess coolant spillage from radiator.
4.Fit plastic plug in radiator.
5.Add a further 1 litre (1.76 pints) of coolant to
expansion tank and allow to settle.
6.Refit expansion tank cap and thermostat
housing plug.
7.Run engine at idle speed for five minutes.
8.Switch off engine, check that expansion tank
coolant is level with top of indicator post and top
up as necessary.Check intercooler and turbo-charger system for air
leaks and pipes/hoses for security and condition.
All system hoses should be renewed at first signs of
deterioration.
VALVE CLEARANCES - CHECK/ADJUST
Check/adjust valve clearances.
See ENGINE ,
Adjustment, Valve clearances - check and adjust
RENEW FUEL FILTER ELEMENT
Remove
1.Clean area around filter head and position a
container beneath.
2.Unscrew and remove filter, catch fuel released.
Refit
3.Wet seal of new filter with fuel.
4.Screw new filter into position.
5.Ensure drain tap is fully closed.
ENGINE
3
REPAIR ENGINE
Service repair no - 12.41.01
Remove
NOTE: A chassis undertray may be fitted
on some vehicle derivatives to conform to
legal requirements. When under chassis
remove and refit procedures are required, it may
be necessary to remove the undertray and/or
integral access panels.
See CHASSIS AND BODY, Repair, Front
undertray
orSee CHASSIS AND BODY, Repair,
Rear undertray
CAUTION: Seal all exposed pipe ends
against ingress of dirt after disconnection.
1.Ensure vehicle is level and apply park brake.
2.Disconnect battery.
NOTE: The vehicle may be fitted with an
alarm and immobilisation system using a
battery backed-up alarm sounder.
See ELECTRICAL, Repair, battery
3.Remove bonnet.
4.Remove cable ties securing gearbox harness to
breather pipes.
5.Disconnect harness from diff lock and reverse
light switches.
6.Manouvre harness into engine bay.
7.Remove air cleaner.
See FUEL SYSTEM,
Repair, Air cleaner
8.Remove radiator assembly.See COOLING
SYSTEM, Repair, Radiator
If air conditioning is fitted the condenser will
have to be removed, compressor pipes and
heater matrix hoses disconnected.
See AIR CONDITIONING, Repair, Condenser
9.Remove rocker cover insulation.
10.Remove feed pipe/hose from turbo-charger and
intercooler.
11.Disconnect heater hoses from cylinder head and
heater rails.
12.Disconnect electrical feed plug at rear of cylinder
head.
13.Disconnect heater plug feed wire.
12ENGINE
6
REPAIR 42.Raise engine, and locate front engine mountings
to chassis.
43.Remove gearbox support and lower engine.
44.Tighten front engine mounting to chassis fixings
to
45 Nm (33 lbf/ft).
45.Release chains from engine lifting brackets and
remove hoist.
46.Connect oil cooler pipes to oil filter adaptor.
47.Fit vacuum hose to brake servo adaptor.
48.Secure fuel feed pipe in retaining clip on air
cleaner bracket.
49.Fit fuel lift pump pipes.
50.Connect feed and spill return pipes to injector
pump.
51.If fitted, reconnect hand throttle cable to
mounting bracket and injector pump.
52.Fit outer cable adjusting nut into injector pump
mounting bracket.
53.Fit inner throttle cable to injector pump and
secure with clevis and split pin.
54.Secure bleed hose in retaining clips on front
timing cover.
55.Fit bleed hose to thermostat housing.
56.Connect inlet and outlet hoses to power steering
pump.
57.Fit down pipe to exhaust manifold and secure
with 3 nuts.
58.Connect starter motor battery and fuse box
leads.
59.If fitted, connect EGR valve multi-plug and
vacuum pipe.
60.Secure breather pipe clip to cylinder head.
61.Connect engine harness multi-plug.
62.Fit heater plug feed wire.
63.Connect electrical feed plug at rear of cylinder
head.
64.Fit heater hoses to cylinder head and heater
rails.
65.Fit feed pipe/hose to turbo-charger and
intercooler.
66.Fit rocker cover insulation.
67.Fit radiator assembly.
See COOLING SYSTEM,
Repair, Radiator
If applicable, fit air
conditioning condenser, compressor pipes and
heater matrix hoses.
See AIR CONDITIONING,
Repair, Condenser
68.Fit bonnet.
69.Reconnect battery.CRANKSHAFT PULLEY
Service repair no - 12.21.01
Remove
1.Disconnect battery.
2.Drain coolant.
See COOLING SYSTEM,
Repair, Drain and refill cooling system
3.Remove top hose from radiator.
4.Remove intercooler to induction manifold hose.
5.Remove viscous coupling and fan.
See
COOLING SYSTEM, Repair, Viscous
coupling and fan
6.Remove fan cowl.See COOLING SYSTEM,
Repair, Fan cowl
7.Remove drive belt.See ELECTRICAL, Repair,
Auxiliary drive belt
8.Fit crankshaft pulley retainerLRT-12-080and
secure with 4 bolts.
9.Remove crankshaft pulley retaining bolt
anti-clockwise using socket and suitable long
bar.
10.Remove pulley retainer.
11.Remove pulley, if necessary using extractor
LRT-12-049with thrust pad fromLRT-12-031.
ENGINE
21
REPAIR 12.Remove induction manifold.
See MANIFOLD
AND EXHAUST SYSTEM, Repair, Induction
manifold
13.Remove exhaust manifold and turbocharger
assembly.
See MANIFOLD AND EXHAUST SYSTEM,
Repair, Exhaust manifold
14.Disconnect heater hose from water pump and
move heater rail aside.
15.Disconnect heater hose from rear of cylinder
head.
16.Remove bolt securing air cleaner mounting
bracket to support strut.
17.Remove bolt securing harness bracket to
cylinder head.
18.Remove rear engine lifting bracket. This will also
release clips securing transmission and engine
breather pipes and multi-plug. Note loose spacer
beneath inner clip.
19.Unscrew 3 bolts, with sealing washers and
remove rocker cover.
20.Remove 3 nuts and 2 bolts and lift rocker shaft
assembly from cylinder head.
21.Remove push rods and store as an identified set
to allow refitment to same location.
22.Remove valve stem caps.
23.Evenly slacken and then remove cylinder head
to block retaining bolts in the sequence shown in
J6157. Two of the bolts also secure the air
cleaner mounting bracket.
24.Lift off cylinder head and remove gasket.
Refit
25.Thoroughly clean mating faces of cylinder block
and head.
26.Select new gasket of correct thickness.
CAUTION: Three gaskets, of different
thicknesses, are available and can be
identified by the number of small holes
punched in the RH side of the gasket. One hole
identifies the thinnest gasket, two holes the
middle thickness and three holes the thickest.
When renewing a gasket it must be of the same
thickness as the one removed.
27.Position gasket on cylinder block with
identification holes on RH side and TOP
identification mark uppermost.