DTC P0461 FUEL LEVEL SENSOR
2007 Versa
5. Turn ignition switch OFF and wait at least 10 seconds then turn
ON.
6. Select “FUEL LEVEL SE” in “DATA MONITOR” mode with CON-
SULT-II.
7. Check “FUEL LEVEL SE” output voltage and note it.
8. Select “FUEL PUMP” in “ACTIVE TEST” mode with CONSULT-
II.
9. Touch “ON” and drain fuel approximately 30 (7-7/8 US gal, 6-
5/8 Imp gal) and stop it.
10. Check “FUEL LEVEL SE” output voltage and note it.
11. Fill fuel into the fuel tank for 30 (7-7/8 US gal, 6-5/8 Imp gal).
12. Check “FUEL LEVEL SE” output voltage and note it.
13. Confirm whether the voltage changes more than 0.03V during step 7 to 10 and 10 to 12.
If NG, go to EC-418, "
Diagnostic Procedure" .
WITH GST
NOTE:
Start from step 8, if it is possible to confirm that the fuel cannot be drained by 30 (7-7/8 US gal, 6-5/8
Imp gal) in advance.
1. Prepare a fuel container and a spare hose.
2. Release fuel pressure from fuel line, refer to EC-81, "
FUEL PRESSURE RELEASE" .
3. Remove the fuel feed hose on the fuel level sensor unit.
4. Connect a spare fuel hose where the fuel feed hose was removed.
5. Turn ignition switch ON.
6. Drain fuel by 30 (7-7/8 US gal, 6-5/8 Imp gal) from the fuel tank using proper equipment.
7. Confirm that the fuel gauge indication varies.
8. Fill fuel into the fuel tank for 30 (7-7/8 US gal, 6-5/8 Imp gal).
9. Confirm that the fuel gauge indication varies.
10. If NG, go to EC-418, "
Diagnostic Procedure" .
Diagnostic ProcedureUBS00QJT
1. CHECK FUEL GAUGE OPERATION
Refer to DI-13, "
Self-Diagnosis Mode of Combination Meter" .
OK or NG
OK >> GO TO 2.
NG >> Follow the instruction of DI-13, "
Self-Diagnosis Mode of Combination Meter" .
2. CHECK FUEL LEVEL SENSOR AND CIRCUIT
Refer to DI-20, "
Fuel Level Sensor Signal Inspection" .
OK or NG
OK >> GO TO 3.
NG >> Repair or replace malfunctioning parts.
3. CHECK INTERMITTENT INCIDENT
Refer to EC-143, "
TROUBLE DIAGNOSIS FOR INTERMITTENT INCIDENT" .
>>INSPECTION END
Removal and InstallationUBS00QJU
FUEL LEVEL SENSOR
Refer to FL-5, "FUEL LEVEL SENSOR UNIT, FUEL FILTER AND FUEL PUMP ASSEMBLY" .
SEF 1 95 Y
Page 1588 of 2896

DTC P0462, P0463 FUEL LEVEL SENSOR
EC-419
C
D
E
F
G
H
I
J
K
L
MA
EC
Revision: June 20062007 Versa
DTC P0462, P0463 FUEL LEVEL SENSORPFP:25060
Component DescriptionUBS00QJV
The fuel level sensor (3) is mounted in the fuel level sensor unit. The
sensor detects a fuel level in the fuel tank and transmits a signal to
the combination meter. The combination meter. sends the fuel level
sensor signal to the ECM through CAN communication line.
It consists of two parts, one is mechanical float and the other is vari-
able resistor. Fuel level sensor output voltage changes depending on
the movement of the fuel mechanical float.
Fuel level sensor unit and fuel pump (1)
Fuel pressure regulator (2)
Fuel tank temperature sensor (4)
On Board Diagnostic LogicUBS00QJW
NOTE:
If DTC P0462 or P0463 is displayed with DTC U1000, U1001, first perform the trouble diagnosis for
DTC U1000, U1001. Refer to EC-151, "
DTC U1000, U1001 CAN COMMUNICATION LINE" .
If DTC P0462 or P0463 is displayed with DTC U1010, first perform the trouble diagnosis for DTC
U1010. Refer to EC-154, "
DTC U1010 CAN COMMUNICATION" .
ECM receives two signals from the fuel level sensor circuit.One is fuel level sensor power supply circuit,
and the other is fuel level sensor ground circuit.This diagnosis indicates the former, to detect open or short
circuit malfunction.
DTC Confirmation ProcedureUBS00QJX
NOTE:
If DTC Confirmation Procedure has been previously conducted, always turn ignition switch OFF and wait at
least 10 seconds before conducting the next test.
TESTING CONDITION:
Before performing the following procedure, confirm that battery voltage is more than 11V at ignition
switch ON.
WITH CONSULT-II
1. Turn ignition switch ON.
2. Select “DATA MONITOR” mode with CONSULT-II.
3. Wait at least 5 seconds.
4. If 1st trip DTC is detected, go to EC-420, "
Diagnostic Procedure"
.
WITH GST
Follow the procedure “WITH CONSULT-II” above.
BBIA0704E
DTC No. Trouble diagnosis name DTC detecting condition Possible cause
P0462
0462Fuel level sensor circuit
low inputAn excessively low voltage from the sensor is
sent to ECM.
Harness or connectors
(CAN communication line is open or
shorted)
Harness or connectors
(Fuel level sensor circuit is open or
shorted)
Combination meter
Fuel level sensor P0463
0463Fuel level sensor circuit
high inputAn excessively high voltage from the sensor is
sent to ECM.
SEF 1 95 Y
Page 1589 of 2896
EC-420Revision: June 2006
DTC P0462, P0463 FUEL LEVEL SENSOR
2007 Versa
Diagnostic ProcedureUBS00QJY
1. CHECK FUEL GAUGE OPERATION
Refer to DI-13, "
Self-Diagnosis Mode of Combination Meter" .
OK or NG
OK >> GO TO 2.
NG >> Follow the instruction of DI-13, "
Self-Diagnosis Mode of Combination Meter" .
2. CHECK FUEL LEVEL SENSOR AND CIRCUIT
Refer to DI-20, "
Fuel Level Sensor Signal Inspection" .
OK or NG
OK >> GO TO 3.
NG >> Repair or replace malfunctioning parts.
3. CHECK INTERMITTENT INCIDENT
Refer to EC-143, "
TROUBLE DIAGNOSIS FOR INTERMITTENT INCIDENT" .
>>INSPECTION END
Removal and InstallationUBS00QJZ
FUEL LEVEL SENSOR
Refer to FL-5, "FUEL LEVEL SENSOR UNIT, FUEL FILTER AND FUEL PUMP ASSEMBLY" .
Page 1739 of 2896

EC-570Revision: June 2006
FUEL PUMP
2007 Versa
FUEL PUMPPFP:17042
DescriptionUBS00PTU
SYSTEM DESCRIPTION
*: ECM determines the start signal status by the signals of engine speed and battery voltage.
The ECM activates the fuel pump for several seconds after the ignition switch is turned ON to improve engine
startability. If the ECM receives a engine speed signal from the crankshaft position sensor (POS) and cam-
shaft position sensor (PHASE), it knows that the engine is rotating, and causes the pump to operate. If the
engine speed signal is not received when the ignition switch is ON, the engine stalls. The ECM stops pump
operation and prevents battery discharging, thereby improving safety. The ECM does not directly drive the fuel
pump. It controls the ON/OFF fuel pump relay, which in turn controls the fuel pump.
COMPONENT DESCRIPTION
A turbine type design fuel pump is used in the fuel tank.
Fuel level sensor unit and fuel pump (1)
Fuel pressure regulator (2)
Fuel level sensor (3)
Fuel tank temperature sensor (4)
CONSULT-II Reference Value in Data Monitor ModeUBS00PTV
Specification data are reference values.
Sensor Input Signal to ECM ECM Function Actuator
Crankshaft position sensor (POS)
Camshaft position sensor (PHASE)Engine speed*
Fuel pump control Fuel pump relay
Battery Battery voltage*
Condition Fuel pump operation
Ignition switch is turned to ON Operates for 1 second
Engine running and crankingOperates
Engine: StoppedStops in 1.5 seconds
Except as shown aboveSto ps
BBIA0704E
MONITOR ITEM CONDITION SPECIFICATION
FUEL PUMP RLY
For 1 second after turning ignition switch ON
Engine running or crankingON
Except above conditions OFF
Page 1740 of 2896
FUEL PUMP
EC-571
C
D
E
F
G
H
I
J
K
L
MA
EC
Revision: June 20062007 Versa
Wiring DiagramUBS00PTW
BBWA2661E
Page 1741 of 2896

EC-572Revision: June 2006
FUEL PUMP
2007 Versa
Specification data are reference values and are measured between each terminal and ground.
CAUTION:
Do not use ECM ground terminals when measuring input/output voltage. Doing so may result in dam-
age to the ECM's transistor. Use a ground other than ECM terminals, such as the ground.
Diagnostic ProcedureUBS00PTX
1. CHECK OVERALL FUNCTION
1. Turn ignition switch ON.
2. Pinch fuel feed hose (1) with two fingers.
–Illustration shows the view with intake air duct removed.
OK or NG
OK >>INSPECTION END
NG >> GO TO 2.
2. CHECK FUEL PUMP POWER SUPPLY CIRCUIT-I
1. Turn ignition switch OFF.
2. Disconnect ECM harness connector.
3. Turn ignition switch ON.
4. Check voltage between ECM terminal 23 and ground with CON-
SULT-II or tester.
OK or NG
OK >> GO TO 5.
NG >> GO TO 3.
TERMI-
NAL
NO.WIRE
COLORITEM CONDITION DATA (DC Voltage)
23 GR Fuel pump relay[Ignition switch: ON]
For 1 second after turning ignition switch ON
[Engine is running]0 - 1.0V
[Ignition switch: ON]
More than 1 second after turning ignition
switch ONBATTERY VOLTAGE
(11 - 14V)
Fuel pressure pulsation should be felt on the fuel
feed hose for 1 second after ignition switch is turned
ON.
BBIA0712E
Voltage: Battery voltage
PBIA9573J
Page 1742 of 2896

FUEL PUMP
EC-573
C
D
E
F
G
H
I
J
K
L
MA
EC
Revision: June 20062007 Versa
3. CHECK FUEL PUMP POWER SUPPLY CIRCUIT-II
1. Turn ignition switch OFF.
2. Disconnect IPDM E/R harness connector E46.
3. Turn ignition switch ON.
4. Check voltage between IPDM E/R terminal 47 and ground with
CONSULT-II or tester.
OK or NG
OK >> GO TO 4.
NG >> GO TO 11.
4. DETECT MALFUNCTIONING PART
Check the following.
Harness connectors E8, F8
Harness for open or short between IPDM E/R and ECM
>> Repair open circuit or short to ground or short to power in harness or connectors.
5. CHECK FUEL PUMP POWER SUPPLY CIRCUIT-III
1. Turn ignition switch OFF.
2. Reconnect all harness connectors disconnected.
3. Disconnect “fuel level sensor unit and fuel pump” harness con-
nector (1).
–Illustration shows the view with inspection hole cover removed.
4. Turn ignition switch ON.
5. Check voltage between “fuel level sensor unit and fuel pump”
terminal 1 and ground with CONSULT-II or tester.
OK or NG
OK >> GO TO 9.
NG >> GO TO 6.Voltage: Battery voltage
PBIB3319E
BBIA0702E
Voltage: Battery voltage should exist for 1 second
after ignition switch is turned ON.
PBIB0795E
Page 1743 of 2896

EC-574Revision: June 2006
FUEL PUMP
2007 Versa
6. CHECK 15A FUSE
1. Turn ignition switch OFF.
2. Disconnect 15A fuse.
3. Check 15A fuse.
OK or NG
OK >> GO TO 7.
NG >> Replace fuse.
7. CHECK FUEL PUMP POWER SUPPLY CIRCUIT-IV
1. Disconnect IPDM E/R harness connector E45.
2. Check harness continuity between IPDM E/R terminal 36 and “fuel level sensor unit and fuel pump” termi-
nal 1. Refer to Wiring Diagram.
3. Also check harness for short to ground and short to power.
OK or NG
OK >> GO TO 13.
NG >> GO TO 8.
8. DETECT MALFUNCTIONING PART
Check the following.
Harness connectors M69, E7
Harness connectors M12, B101
Harness for open or short between IPDM E/R and “fuel level sensor unit and fuel pump”
>> Repair open circuit or short to ground or short to power in harness or connectors.
9. CHECK FUEL PUMP GROUND CIRCUIT
1. Check harness continuity between “fuel level sensor unit and fuel pump” terminal 3 and ground.
Refer to Wiring Diagram.
2. Also check harness for short to power.
OK or NG
OK >> GO TO 10.
NG >> Repair or replace harness or connectors.
10. CHECK FUEL PUMP
Refer to EC-575, "
Component Inspection" .
OK or NG
OK >> GO TO 11.
NG >> Replace fuel pump.
11 . CHECK INTERMITTENT INCIDENT
Refer to EC-143, "
TROUBLE DIAGNOSIS FOR INTERMITTENT INCIDENT" .
OK or NG
OK >> Replace IPDM E/R. Refer to PG-29, "Removal and Installation of IPDM E/R" .
NG >> Repair or replace harness or connectors.Continuity should exist.
Continuity should exist.