EM-70
[QR]
CYLINDER HEAD
CYLINDER HEADPFP:11041
On-Vehicle ServiceEBS00KNP
CHECKING COMPRESSION PRESSURE
1. Warm up engine thoroughly. Then, stop it.
2. Release fuel pressure. Refer to EC-49, "
FUEL PRESSURE RELEASE" (WITH EURO-OBD) or EC-562,
"FUEL PRESSURE RELEASE" (WITHOUT EURO-OBD).
3. Disconnect fuel pump fuse to avoid fuel injection during mea-
surement.
4. Remove ignition coil and spark plug from each cylinder. Refer to EM-31, "
IGNITION COIL" and EM-32,
"SPARK PLUG" .
5. Connect engine tachometer (not required in use of CONSULT-II).
6. Install compression tester with adapter onto spark plug hole.
Use the adapter whose picking up end inserted to spark plug
hole is smaller than 20 mm (0.79 in) in diameter. Otherwise, it
may be caught by cylinder head during removal.
7. With accelerator pedal fully depressed, turn ignition switch to “START” for cranking. When the gauge
pointer stabilizes, read the compression pressure and engine rpm. Perform these steps to check each cyl-
inder.
Compression pressure:
Unit: kPa (bar, kg/cm2 , psi) /rpm
CAUTION:
Always use a fully changed battery to obtain specified engine speed.
PBIB0508E
KBIA0130E
SBIA0533E
Engine type Standard Minimum Differential limit between cylinders
QR20DE 1,190 (11.9, 12.1, 173) / 250 990 (9.9, 10.1, 144) / 250
100 (1.0, 1.0, 14) / 250
QR25DE 1,250 (12.5, 12.8, 181) / 250 1,060 (10.6, 10.8, 154) / 250
CYLINDER HEAD
EM-73
[QR]
C
D
E
F
G
H
I
J
K
L
MA
EM
INSTALLATION
1. Install cylinder head gasket.
2. Tighten cylinder head bolts in numerical order as shown in figure
with the following procedure, and install cylinder head.
CAUTION:
If cylinder head bolts are re-used, check their outer diame-
ters before installation. Refer to EM-72, "
Cylinder Head
Bolts Outer Diameter" .
a. Apply new engine oil to threads and seating surface of mounting
bolts.
b. Tighten all bolts.
c. Turn all bolts 60 degrees clockwise (angle tightening).
d. Completely loosen.
CAUTION:
In this step, loosen bolts in reverse order of that indicated in the figure.
e. Tighten all bolts.
f. Turn all bolts 75 degrees clockwise (angle tightening).
g. Turn all bolts 75 degrees clockwise again (angle tightening).
CAUTION:
Check and confirm the tightening angle by using an angle
wrench (special service tool) or protractor. Avoid judgment
by visual inspection without the tool.
3. Install in the reverse order of removal after this step.
INSPECTION AFTER INSTALLATION
Inspection for Leaks
The following are procedures for checking fluids leak, lubricates leak and exhaust gases leak.
Before starting engine, check oil/fluid levels including engine coolant and engine oil. If less than required
quantity, fill to the specified level. Refer to MA-17, "
RECOMMENDED FLUIDS AND LUBRICANTS" .
Use procedure below to check for fuel leakage.
–Turn ignition switch “ON” (with engine stopped). With fuel pressure applied to fuel piping, check for fuel
leakage at connection points.
–Start engine. With engine speed increased, check again for fuel leakage at connection points.
Run engine to check for unusual noise and vibration.
Warm up engine thoroughly to make sure there is no leakage of fuel, exhaust gases, or any oil/fluids
including engine oil and engine coolant.
Bleed air from lines and hoses of applicable lines, such as in cooling system.
After cooling down engine, again check oil/fluid levels including engine oil and engine coolant. Refill to the
specified level, if necessary. : 50 N·m (5.1 kg-m, 37 ft-lb)
: 0 N·m (0 kg-m, 0 ft-lb)
: 39.2 N·m (4.0 kg-m, 29 ft-lb)
KBIA0058E
KBIA0059E
EM-74
[QR]
CYLINDER HEAD
Summary of the inspection items:
* Transmission/transaxle/CVT fluid, power steering fluid, brake fluid, etc.
Disassembly and AssemblyEBS00KNR
DISASSEMBLY
1. Remove spark plug with spark plug wrench (commercial service tool).
2. Remove spark plug tube, if necessary.
Using pliers, remove it from cylinder head.
CAUTION:
Be careful not to damage cylinder head.
Do not remove spark plug tube if not necessary. Once removed, spark plug tube cannot be
reused because of deformation.
3. Remove valve lifter.
Identify installation positions, and store them without mixing them up.
4. Remove valve collet.
Item Before starting engine Engine running After engine stopped
Engine coolant Level Leakage Level
Engine oil Level Leakage Level
Other oils and fluid* Level Leakage Level
Fuel Leakage Leakage Leakage
Exhaust gases — Leakage —
1. Valve collet 2. Valve spring retainer 3. Valve spring (with valve spring seat)
4. Valve oil seal 5. Valve guide 6. Cylinder head
7. Valve seat 8. Valve (INT) 9. Valve (EXH)
10. Spark plug tube 11. Spark plug
PBIC2629E
ENGINE ASSEMBLY
EM-81
[QR]
C
D
E
F
G
H
I
J
K
L
MA
EM
ENGINE ASSEMBLYPFP:10001
Removal and Installation (2WD Models)EBS01FKJ
WARNING:
Situate the vehicle on a flat and solid surface.
Place chocks at front and back of rear wheels.
For engines not equipped with engine slingers, attach proper slingers and bolts described in
PARTS CATALOG.
CAUTION:
Always be careful to work safely, avoid forceful or uninstructed operations.
Do not start working until exhaust system and coolant are cool enough.
If items or work required are not covered by the engine section, refer to the applicable sections.
Always use the support point specified for lifting.
Use either 2-pole lift type or separate type lift as best you can. If board-on type is used for
unavoidable reasons, support at the rear axle jacking point with a transmission jack or similar tool
before starting work, in preparation for the backward shift of center of gravity.
For supporting points for lifting and jacking point at rear axle, refer to GI-36, "Garage Jack and
Safety Stand" .
1. Rear engine mounting insulator 2. Rubber seat 3. Rear engine mounting bracket
4. RH engine mounting insulator 5. RH engine mounting bracket 6. Front engine mounting bracket
7. Front engine mounting insulator 8. Grommet 9. Center member
10. LH engine mounting insulator 11. Stopper 12. LH engine mounting bracket
PBIC3831E
EM-84
[QR]
ENGINE ASSEMBLY
INSPECTION AFTER INSTALLATION
Inspection for Leaks
The following are procedures for checking fluids leak, lubricates leak and exhaust gases leak.
Before starting engine, check oil/fluid levels including engine coolant and engine oil. If less than required
quantity, fill to the specified level. Refer to MA-17, "
RECOMMENDED FLUIDS AND LUBRICANTS" .
Use procedure below to check for fuel leakage.
–Turn ignition switch “ON” (with engine stopped). With fuel pressure applied to fuel piping, check for fuel
leakage at connection points.
–Start engine. With engine speed increased, check again for fuel leakage at connection points.
Run engine to check for unusual noise and vibration.
Warm up engine thoroughly to make sure there is no leakage of fuel, exhaust gases, or any oil/fluids
including engine oil and engine coolant.
Bleed air from lines and hoses of applicable lines, such as in cooling system.
After cooling down engine, again check oil/fluid levels including engine oil and engine coolant. Refill to the
specified level, if necessary.
Summary of the inspection items:
* Transmission/transaxle/CVT fluid, power steering fluid, brake fluid, etc.Item Before starting engine Engine running After engine stopped
Engine coolant Level Leakage Level
Engine oil Level Leakage Level
Other oils and fluid* Level Leakage Level
Fuel Leakage Leakage Leakage
Exhaust gases — Leakage —
ENGINE ASSEMBLY
EM-85
[QR]
C
D
E
F
G
H
I
J
K
L
MA
EM
Removal and Installation (4WD Models)EBS00KNT
WARNING:
Situate vehicle on a flat and solid surface.
Place chocks at front and back of rear wheels.
For engines not equipped with engine slingers, attach proper slingers and bolts described in
PARTS CATALOG.
CAUTION:
Always be careful to work safely, avoid forceful or uninstructed operations.
Do not start working until exhaust system and engine coolant are cool enough.
If items or work required are not covered by the engine section, refer to the applicable sections.
Always use the support point specified for lifting.
Use either 2-pole lift type or separate type lift as best you can. If board-on type is used for
unavoidable reasons, support at the rear axle jacking point with transmission jack or similar tool
before starting work, in preparation for the backward shift of center of gravity.
For supporting points for lifting and jacking point at rear axle, refer to GI-36, "Garage Jack and
Safety Stand" .
REMOVAL
Outline
Remove engine, transaxle and transfer assembly with front suspension member from vehicle downward. Sep-
arate front suspension member, and then separate engine and transaxle.
Preparation
1. Remove hood assembly. Refer to BL-12, "HOOD" .
1. Rear engine mounting insulator 2. Rear engine mounting bracket 3. RH engine mounting insulator
4. RH engine mounting bracket 5. Front engine mounting bracket 6. Front engine mounting insulator
7. Center member 8. LH engine mounting insulator 9. LH engine mounting bracket
10. Stopper 11. Grommet
PBIC3830E
EM-88
[QR]
ENGINE ASSEMBLY
9. Remove power steering oil pump with piping connected from engine. Move it aside on front suspension
member. Refer to PS-37, "
HYDRAULIC LINE" .
10. Remove front engine mounting and rear engine mounting through-bolts to remove front suspension mem-
ber and center member.
11. Remove starter motor. Refer to SC-23, "
STARTING SYSTEM" .
12. Separate engine and transaxle. Refer to MT-19, "
TRANSAXLE ASSEMBLY" (M/T models) or AT- 4 1 3 ,
"REMOVAL AND INSTALLATION" (A/T models).
INSTALLATION
Note the following, and install in the reverse order of removal.
Do not allow engine oil to get on engine mounting insulator. Be careful not to damage engine mounting
insulator.
When installation directions are specified, install parts according to the direction marks on them referring
to figure of components. Refer to EM-85, "
Removal and Installation (4WD Models)" .
Make sure that each mounting insulator is seated properly, and tighten mounting bolts and nuts.
INSPECTION AFTER INSTALLATION
Inspection for Leaks
The following are procedures for checking fluids leak, lubricates leak and exhaust gases leak.
Before starting engine, check oil/fluid levels including engine coolant and engine oil. If less than required
quantity, fill to the specified level. Refer to MA-17, "
RECOMMENDED FLUIDS AND LUBRICANTS" .
Use procedure below to check for fuel leakage.
–Turn ignition switch “ON” (with engine stopped). With fuel pressure applied to fuel piping, check for fuel
leakage at connection points.
–Start engine. With engine speed increased, check again for fuel leakage at connection points.
Run engine to check for unusual noise and vibration.
Warm up engine thoroughly to make sure there is no leakage of fuel, exhaust gases, or any oil/fluids
including engine oil and engine coolant.
Bleed air from lines and hoses of applicable lines, such as in cooling system.
After cooling down engine, again check oil/fluid levels including engine oil and engine coolant. Refill to the
specified level, if necessary.
Summary of the inspection items:
* Transmission/transaxle/CVT fluid, power steering fluid, brake fluid, etc.Item Before starting engine Engine running After engine stopped
Engine coolant Level Leakage Level
Engine oil Level Leakage Level
Other oils and fluid* Level Leakage Level
Fuel Leakage Leakage Leakage
Exhaust gases — Leakage —
EM-96
[QR]
CYLINDER BLOCK
ii. Tighten M8 bolts in numerical order from No. 11 to 22 in the fig-
ure.
NOTE:
There are more processes to complete the tightening of mount-
ing bolts. However stop procedure here to install rear oil seal.
c. Install rear oil seal. Refer to EM-68, "
Removal and Installation of Rear Oil Seal" .
d. Restart tightening of lower cylinder block mounting bolts with the following procedure:
i. Tighten M10 bolts in numerical order from No. 1 to 10.
ii. Turn M10 bolts 60 degrees clockwise (angle tightening) in order
from No. 1 to 10 in the figure.
CAUTION:
Check and confirm the tightening angle by using an angle
wrench (special service tool) or protractor. Avoid judgment
by visual inspection without the tool.
After installing mounting bolts, make sure that crankshaft can be rotated smoothly by hand.
Wipe off completely any protruding liquid gasket on front side of engine.
Check crankshaft end play. Refer to EM-107, "CRANKSHAFT END PLAY" .
7. Install piston to connecting rod with the following procedure:
a. Using snap ring pliers, install new snap ring to the groove of the piston rear side.
Insert it fully into groove to install.
b. Assemble piston to connecting rod.
Using an industrial use drier or similar tool, heat the piston until the piston pin can be pushed in by hand
without excess force [approx. 60 to 70 °C (140 to 158 °F)]. From the front to the rear, insert piston pin
into piston and connecting rod. : 25.1 N·m (2.6 kg-m, 19 ft-lb)
KBIA0063E
: 39.2 N·m (4.0 kg-m, 29 ft-lb)
KBIA0063E
KBIA0065E