ENGINECHECKING AND SETTING THE VALVE TIMING
Engine: WJY
B1EP1EDC
Setting the timing (continued).
NOTE:If necessary, you can slightly rotate the pinions (10)and (7)anti-clockwise in order to engage the belt.
The angular displacement value of the belt in relation to the pinions should not be more than half a tooth.
Remove tool [5].
Act on the tensioner roller (8)by its square «a», using tool [6]to check that the camshaft and injection
pump pinions can turn freely.
Position the belt tension instrument [7]on the belt at «b».
Using tool [6], act at «a»in the direction opposite to that of engine rotation, to obtain a tension value of
106 ± 2 SEEMunits.
Tighten screws (9), (5) and (6).
Remove tools [7], [2], [3]and [4].
Rotate the crankshaft 8 times
in the normal direction of rotation.
Peg the flywheel, using tool [2].
Peg the camshaft hub, using tool [4].
Peg the injection pump hub, using tool [3].
Slacken screws (9), (5)and (6).
Position the belt tension instrument [7]on the belt at «b».
Using tool [6], act at «a»in the direction opposite to that of engine rotation, to obtain a tension value of
42 ± 2 SEEMunits.
B1EP1EFC
XSARA
Angl.-t2-page240-282-2005 9/01/06 10:16 Page 262
Page 269 of 462

Downloaded from www.Manualslib.com manuals search engine 263
ENGINE
CHECKING AND SETTING THE VALVE TIMING
Engine: WJY
Setting the timing (continued).
Tighten:
- Screw (9)to 2.1 ± 0.2 m.daN.
- Screws (5)to 2,3 ± 0.2 m.daN.
- Screws (6)to 2,3 ± 0.2 m.daN.
- Remove and refit tool [7].
- The tension value should be between 38 and 46 SEEMunits.
- Remove tools [7], [2], [3]and [4].
- Turn the crankshaft 2 times
in the normal direction of rotation.
- Peg the flywheel, using the peg [2].
- Visually check the peggings of the camshaft and injection pump.
ESSENTIAL: Visually check that the offsets between the holes of
the camshaft and injection pump hubs and the corresponding
pegging holes are not more than 1 mm. If necessary, recommence
the procedure for fitting the timing belt.
XSARA
Setting the timing (continued).
Remove the peg [2].
Remove the screw (4)and the washer.
Refit the lower cover (3).
Refit the intermediate cover (2).
Refit the upper cover (1).
Remove the RH engine support.
Take away the workshop hoist.
Remove the plugs and recouple the diesel fuel delivery and return
hoses.
Refit the accessories drive belt
(see corresponding operation).
Refit the RH lower splash-shield.
Disengage 5th gear.
Connect the battery.
Angl.-t2-page240-282-2005 9/01/06 10:16 Page 263
Page 270 of 462
![Citroen XSARA PICASSO 2005 1.G Workshop Manual Downloaded from www.Manualslib.com manuals search engine 264
ENGINECHECKING AND SETTING THE VALVE TIMING
Tools.
[1]Belt tension measuring equipment : 4122-T
[2]Tension lever: (-).0188.J2
[3]Engine fly Citroen XSARA PICASSO 2005 1.G Workshop Manual Downloaded from www.Manualslib.com manuals search engine 264
ENGINECHECKING AND SETTING THE VALVE TIMING
Tools.
[1]Belt tension measuring equipment : 4122-T
[2]Tension lever: (-).0188.J2
[3]Engine fly](/manual-img/9/4138/w960_4138-269.png)
Downloaded from www.Manualslib.com manuals search engine 264
ENGINECHECKING AND SETTING THE VALVE TIMING
Tools.
[1]Belt tension measuring equipment : 4122-T
[2]Tension lever: (-).0188.J2
[3]Engine flywheel peg: (-).0188.Y
[4] Belt clamp: (-).0188.AD
[5]Camshaft pulley peg: (-).0188.M
[6] Engine flywheel lock: (-).0188.F
[7] Set of blocking plugs: (-).0188.T
[8] Pulley extractor: (-).0188.P
[9] 2 mm Øpeg: (-).0188.Q2Removing.
IMPERATIVE: Respect the safety and cleanliness requirements
that are specific to high pressure diesel injection (HDi) engines.
Undo the front RH wheel bolts.
Raise and support the vehicle on the front RH side.
Disconnect the battery negative terminal.
Remove:
- The under-engine sound-deadening.
- The front RH wheel.
- The front RH splash-shield.
- The engine cover.
Unclip and move aside the cooling hose.
Remove the accessories drive belt
(see corresponding operation).
XSARA - XSARA PICASSO
Engines: RHY - RHZ
Angl.-t2-page240-282-2005 9/01/06 10:16 Page 264
Page 271 of 462
Downloaded from www.Manualslib.com manuals search engine 265
ENGINE
CHECKING AND SETTING THE VALVE TIMING
Engines: RHY - RHZ
Uncouple, plug and move aside, using tool [7], the fuel delivery pipe(2)and return
pipe (1).
Remove:
- Screws (3), (4)and (6).
- Screw (7).
- The upper timing cover (5).
WARNING: Refit screw (7) equipped with a spacer
(17 mm thick), tighten the
screw (7) to 1,5 ± 0,1 m. daN.
NOTE: The screw (7)is one of the screws securing the coolant pump and is there
for its sealing.
Put the gear lever in 5th gear.
Turn the road wheel to turn the engine in its direction of rotation.
Orient the camshaft pulley in the pegging position, use a mirror if necessary.
Peg the camshaft, using tool [5].
Peg the engine flywheel, using tool [3].
B1EP1A7CB1BP2H3CB1BP2H2CB1BP2R2C
XSARA - XSARA PICASSO
Angl.-t2-page240-282-2005 9/01/06 10:16 Page 265
Page 272 of 462
Downloaded from www.Manualslib.com manuals search engine 266
ENGINECHECKING AND SETTING THE VALVE TIMING
Engines: RHY - RHZ
Remove:
- The fixings of the pipe linking the power steering pump with the rotary valve.
- The clutch lower closing plate.
- Lock the engine flywheel, using tool [6].
Remove the screw (8).
Refit the screw (8)without its thrust washer.
Remove:
- The accessories pulley (9), using tool [8].
- Tool [6].
- The lower torque reaction rod.
Support the engine by means of a workshop hoist.
Remove:
- The bearing shell fitting (10).
- The nut (12).
- Screws (11).
- The bracket (13).
NOTE:Lift then lower the engine with the workshop hoist, to have access to the
timing cover fixing screws.
Remove:
- The intermediate timing cover.
- The lower timing cover.
B1CP04BCB1BP2R3CB1BP2R4C
XSARA - XSARA PICASSO
Angl.-t2-page240-282-2005 9/01/06 10:16 Page 266
Page 273 of 462
Downloaded from www.Manualslib.com manuals search engine 267
ENGINE
CHECKING AND SETTING THE VALVE TIMING
Engines: RHY - RHZ
Slacken the screw (17)of the tensioner roller (18).
Remove the timing belt (14).
Checks.
IMPERATIVE: Just before refitting, carry out the checks below.
Check that:
- The rollers (18)and (15)turn freely
(without play and without any tight spot).
- The coolant pump pulley (16)turns freely
(without play and without any tight spot).
- There are no traces of oil leaks from the crankshaft and camshaft seals, etc.
- The crankshaft pinion travels freely on the keyway.
Replace defective components if necessary.
Peg the crankshaft pinion (19)by inserting tool [9]on the LH side of the keyway.
B1EP1A8D
B1EP1A9C
XSARA - XSARA PICASSO
Angl.-t2-page240-282-2005 9/01/06 10:16 Page 267
Page 274 of 462
Downloaded from www.Manualslib.com manuals search engine 268
ENGINECHECKING AND SETTING THE VALVE TIMING
Engines: RHY - RHZ
Reposition the timimg belt, belt at «a»well tensioned, in the following order:
- Fuel high pressure pump pulley (21).
- Guide roller (15).
- Crankshaft pinion (19).
- Coolant pump pinion (16).
- Tensioner roller (18).
Position tool [1]on the belt at «a».
Remove tools [4]and [9].
Turn the tensioner roller (18)anti-clockwise, using tool [2], to attain an overtension of:
98 ± 2 SEEMunits.
Tighten screw (17)of the tensioner roller to 2,5 ± 0,2 m.da N.
Lock the flywheel by means of tool [6].
Tighten the accessories drive pulley screw (8)to 7 ± 0,7 m.da N.
Remove tools [1], [3], [5]and [6].
Rotate the crankshaft eight times in the normal direction of rotation.
Peg:
- The crankshaft, using tool [3].
- The camshaft drive pulley, using tool [5].
B1EP1ABD
B1EP1ACC
XSARA - XSARA PICASSO
Angl.-t2-page240-282-2005 9/01/06 10:16 Page 268
Page 275 of 462
Downloaded from www.Manualslib.com manuals search engine 269
ENGINE
CHECKING AND SETTING THE VALVE TIMING
Engines: RHY - RHZ
Lock the engine flywheel, using tool [6].
Slacken the accessories drive pulley (8).
The screw (17)of the tensioner roller (18).
Fit the tool [1].
Turn the tensioner roller, using tool [2], to attain a tension of: 54 ± 2 SEEMunits.
Tighten screw (17)of the tensioner roller (18)to 2,5 ± 0,2 m.daN.
Remove tool [1].
Fit tool [1].
The tension value should be: 54 ± 3 SEEMunits.
ESSENTIAL: If the value is incorrect, recommence the operation.
Remove tools [1], [3], [5]and [6].
Rotate the crankshaft two times in the normal direction of rotation.
Peg:
- The crankshaft, using tool [3].
- The camshaft drive pulley.
IMPERATIVE: If the pegging is not possible, recommence the operation.