Page 112 of 801

YH4
GRAND
VITARA
AIR CONDITIONING (OPTIONAL) 1B-41
INSPECTION
1) Check evaporator fins for blockage. If found clogged, use com-
pressed air to clean the fins.
CAUTION:
Do not use water for cleaning of evaporator.
Be careful not to damage evaporator fins. If evaporator
fin is bent, straighten it by using a screwdriver or pair of
pliers. If any leakage is found from fitting or tube, repair
or replace evaporator.
2) Check inlet and outlet fittings for crack or scratch. Repair them
as required.
REASSEMBLY and INSTALLATION
1) Reverse removal and disassembly sequence to install cooling
unit, noting the following points.
Install uniformly the evaporator packing to dash panel hole for
expansion valve.
Adjust fresh air control cable, refer to ªHEATER CONTROL
LEVER ASSEMBLYº in Section 1A.
2) Enable air bag system. Refer to ªEnabling Air Bag Systemº in
Section 10B.
3) Evacuate and charge system. Refer to ªEVACUATINGº and
ªCHARGINGº in this section.
NOTE:
When the thermistor removed, it should be reinstalled in
original position.
If cooling unit or evaporator is replaced, pour 25 cc of refrig-
erating oil to compressor suction-side.
Page 115 of 801
YH4
GRAND
VITARA
1B-44 AIR CONDITIONING (OPTIONAL)
REFRIGERANT PIPES AND HOSES
INSPECTION
1) Use a leak tester to check hoses and pipes for any gas leakage.
2) Check each hose or pipe clamp for tightness.
Retighten or replace loose clamp as required, if any.
REMOVAL
1) Recover refrigerant by using recovery and recycling equipment.
Be sure to follow the instruction manual for the equipment.
The amount of compressor oil removed must be measured and
the same amount must be added to the system when reinstal-
ling.
2) Replace defective hose or pipe.
CAUTION:
As soon as the above hose or pipe is disconnected, cap
its opened fitting to prevent moisture and dust from en-
tering.
INSTALLATION
1) Reverse removal procedure to install refrigerant line.
2) Evacuate and charge system. Refer to ªEVACUATINGº and
ªCHARGINGº in this section.
INSPECTION OF IDLE SPEED WITH A / C ON
For G16 and J20 engines model, refer to Section 6E1.
For H25 engine model, refer to Section 6E2.
Page 118 of 801
YH4
GRAND
VITARA
Pressure ABCD SWITCH
ON
(Continuity)
OFF
(No continuity)
AIR CONDITIONING (OPTIONAL) 1B-47
DUAL PRESSURE SWITCH
INSPECTION
1) Check dual pressure switch (1) on liquid pipe for continuity at
normal temperature (approx. 25C (77F)) when A / C system
has a proper charge of refrigerant and when A / C system (com-
pressor) is under operation. In each of these cases, switch
should show proper continuity.
2) Using a manifold gauge set, check switch for operation at speci-
fied pressure as shown, refer to ªPERFORMANCE DIAGNO-
SISº in this section.
Switch ON : above ªCº and below ªDº
Switch OFF : below ªAº or above ªBº
ªAº: Approx. 200 kPa (2.0 kg / cm
2)
ªBº: Approx. 3200 kPa (32 kg / cm
2)
ªCº: Approx. 230 kPa (2.3 kg / cm
2)
ªDº: Approx. 2800 kPa (28 kg / cm
2)
Tightening torque:
Dual pressure switch: 10 N
.m (1.0 kg-m, 7.5 lb-ft)
Page 121 of 801
YH4
GRAND
VITARA
1B-50 AIR CONDITIONING (OPTIONAL)
REMOVAL
1) Run engine at idle with A / C ON for 10 minutes.
2) Disconnect negative (±) cable at battery.
3) Recover refrigerant from refrigeration system using recovery
and recycling equipment.
NOTE:
The amount of compressor oil at removed must be mea-
sured and the same amount must be poured when installing
the compressor.
4) Disconnect thermal protector lead wire.
5) Disconnect suction and discharge hoses from compressor as-
sembly.
NOTE:
Cap open fitting immediately to keep moisture out of sys-
tem.
6)For G16 engine:
Remove compressor drive belt by loosening compressor as-
sembly mounting bolts.
For J20 engine:
Remove generator belt. Refer to Section 6H.
For H25 engine:
Remove compressor drive belt by loosening tension pulley bolt.
7) Remove compressor with magnet clutch assembly from its
mount.
8) If compressor assembly is replaced. Drain oil from compressor
assembly, and measure its amount.
Page 122 of 801

YH4
GRAND
VITARA
AIR CONDITIONING (OPTIONAL) 1B-51
G16 engine
J20 engine
H25 engine
3. Compressor pulley
4. Crankshaft pulley
INSTALLATION
FOR IWATA PRODUCTION VEHICLE
1) Pour new compressor oil. The amount must be the same with
the amount measured in REMOVAL.
NOTE:
Compressor assembly supplied from factory is filled up
with following amount of oil.
Amount of oil in compressor: 120 cm
3 (120 cc, 7.5 in3)
2)For G16 engine:
Install compressor assembly temporarily to bracket, then install
compressor drive belt (2).
For J20 and H25 engines:
Install compressor assembly to its bracket.
Tighten bolts (a) first, then (b).
Tightening Torque
(a), (b): 23 N
.m (2.3 kg-m, 17.0 lb-ft)
3) Connect suction and discharge hoses to compressor assembly.
4)For G16 engine:
Tension compressor drive belt (2) by tightening compressor as-
sembly mounting bolts. Refer to Section 3B1 for drive belt ten-
sion.
Tighten bolt (a) first, then (b).
Tightening Torque
(a), (b): 23 N
.m (2.3 kg-m, 17.0 lb-ft)
For J20 engine:
Install generator belt (1). Refer to Section 6H for details.
For H25 engine:
Install compressor drive belt (2). Refer to Section 3B1 for instal-
lation and belt tension.
5) Connect thermal protector lead wire.
6) Evacuate and charge system according to previously described
procedure.
CAUTION:
Be sure to use HFC-134a (R-134a) compressor oil.
Page 123 of 801

YH4
GRAND
VITARA
1B-52 AIR CONDITIONING (OPTIONAL)
G16 engine
J20 engine
3. Compressor pulley
4. Crankshaft pulley
FOR CAMI PRODUCTION VEHICLE
1) Pour new compressor oil. The amount must be the same with
the amount measured in REMOVAL.
NOTE:
Compressor assembly supplied from factory is filled up
with the following amount of oil.
Amount of oil in compressor: 120 cm
3 (120 cc, 7.5 in3)
2)For G16 engine:
Install compressor assembly temporarily to bracket, then install
compressor drive belt (2).
For J20 engine:
Install compressor assembly to its bracket.
Tighten bolts (a).
Tightening Torque
(a): 23 N
.m (2.3 kg-m, 17.0 lb-ft)
3) Connect suction and discharge hoses to compressor assembly.
4)For G16 engine:
Tension compressor drive belt (2) by tightening compressor as-
sembly mounting bolts. Refer to Section 3B1 for drive belt ten-
sion.
Tighten bolt (a) first, then (b).
Tightening Torque
(a): 23 N
.m (2.3 kg-m, 17.0 lb-ft)
For J20 engine:
Install generator belt (1). Refer to Section 6H for details.
5) Connect thermal protector lead wire.
6) Evacuate and charge system according to previously described
procedure.
CAUTION:
Be sure to use HFC-134a (R-134a) compressor oil.
Page 126 of 801
YH4
GRAND
VITARA
AIR CONDITIONING (OPTIONAL) 1B-55
1. Armature plate
4) Clutch pulley (1).
(1) Set clutch pulley squarely over clutch pulley installation boss.
(2) Place special tool (D) onto clutch pulley bearing.
Ensure that edge rests only on inner race of bearing.
(3) Install snap ring.
Special Tool
(D): 09991-06010
CAUTION:
Be careful not to scratch bearing seal.
5) Adjust clearance, between clutch plate (1) and clutch pulley by
putting shim on compressor shaft.
Standard clearance ªaº: 0.3 ± 0.5 mm (0.012 ± 0.02 in.)
6) Tighten new clutch plate bolt as specified below.
Tightening Torque
(a): 14 N
.m (1.4 kg-m, 10.5 lb-ft)
Special Tool
(A): 09991-06020
Page 129 of 801
YH4
GRAND
VITARA
3. Washer
(if equipped)
1B-58 AIR CONDITIONING (OPTIONAL)
4) Install clutch pulley (1).
(1) Set clutch pulley squarely over clutch pulley installation boss.
(2) Place special tool (D) onto clutch pulley bearing.
Ensure that edge rests only on inner race of bearing.
(3) Install snap ring.
Special Tool
(D): 09991-06010
CAUTION:
Be careful not to scratch bearing seal.
5) Adjust clearance, between clutch plate and clutch pulley (2) by
putting shim on compressor shaft.
Standard clearance ªaº: 0.3 ± 0.6 mm (0.012 ± 0.024 in.)
6) Tighten new clutch plate (1) bolt (2) as specified below.
Tightening Torque
(a): 14 N
.m (1.4 kg-m, 10.5 lb-ft)
Special Tool
(A): 09991-06020