349
*
[SV50050( EF )10/90]
NOTE: All current model year vehicles are
certified to the same year emissions
standards except certain vehicles
equipped with engines built prior to
January 1 of the model year which may
be certified to prior year emissions
standards. In either case, the
maintenance schedules contained in the
back of this Owner Guide must be
used to maintain your engine.
%*
[SV50100( EFM)01/89]
Noise emissions warranty, prohibited
tampering acts
[SV50300( E )03/93]
On January 1, 1978, Federal regulations became
effective governing the noise emissions on trucks
with a GVWR of over 10,000 lbs (4,536 kgs). The
following statements concerning prohibited
tampering acts and the noise warranty are found
in theWarranty Information Booklet, and are
applicable to completed Econoline cutaways with
a GVWR of over 10,000 lbs (4,536 kgs).
*
[SV50400( EFM)01/89]
Do not tamper with the noise control
system
*
[SV50500( EFM)01/89]
Federal law prohibits the following acts:
*
[SV50600( EFM)01/89]
1. The removal or dismantlement, (by any
person unless for maintenance, repair or
replacement purposes) of any device or
design element incorporated into any new
vehicle to control noise output, prior to its
sale or delivery to the consumer, or while it
is being used, or
*
[SV50700( EFM)01/89]
2. Using your light truck after a device or
design element has been removed or
dismantled, by any person.
File:14ltsve.ex
Update:Wed Apr 17 08:40:13 1996
351 %
*
[SV51456( ALL)06/95]
Readiness for Inspection/Maintenance
Testing
*
[SV51457( ALL)06/95]
In some localities it may become a legal
requirement to pass an
Inspection/Maintenance (I/M) test of the
On-Board Diagnostic (OBD) II system. If the
vehicle's powertrain system or its battery has
just been serviced, the OBD II system is reset to
a not ready for I/M testing condition. To
prepare for I/M testing, the law specifies a
ªneed for additional mixed city and highway
driving to complete the checkº of the OBD II
system. As soon as all of the OBD II system
checks are successfully completed, the OBD II
system is set to the ready condition. The amount
of driving required to reach the ready condition
varies with individual driving patterns. To
complete this requirement in the minimum
amount of time, refer to the OBD II Drive Cycle
defined below. If the vehicle owner cannot or
does not want to do the additional driving
required by law, a service center can perform
this drive cycle as it would any other type of
repair work.
[SV51458( ALL)05/95]
OBD II Drive Cycle
*
[SV51459( ALL)05/95]
The engine must be warmed up and at
operating temperature before proceeding with
the drive modes of the following OBD II Drive
Cycle.
*
[SV51461( ALL)05/95]
1. Start the engine. Drive or idle (in neutral)
the vehicle for 4 minutes.
[SV51463( ALL)04/95]
2. Idle the vehicle in drive (neutral for manual
transmission) for 40 seconds.
*
[SV51465( ALL)06/95]
3. Accelerate the vehicle to 45 mph (70 km/h)
at 1/4 to 1/2 throttle for 10 seconds.
File:14ltsve.ex
Update:Wed Apr 17 08:40:13 1996
352
*
[SV51467( ALL)06/95]
4. Drive the vehicle with a steady throttle at
45 mph (70 km/h) for 30 seconds.
*
[SV51469( ALL)05/95]
5. Idle the vehicle in Drive (Neutral for manual
transmissions) for 40 seconds.
*
[SV51471( ALL)06/95]
6. Continue to drive the vehicle in city traffic at
speeds between 25 and 40 mph
(40-60 km/h) for 15 minutes. During the 15
minute drive cycle the following modes must
be achieved:
*
[SV51473( ALL)06/95]
a. at least 5 stop and idle modes at 10
seconds each
*
[SV51475( ALL)06/95]
b. acceleration from idles at 1/4 to 1/2
throttle position, and
*
[SV51477( ALL)06/95]
c. choose 3 different speeds to do 1.5
minute steady state throttle drives.
*
[SV51479( ALL)06/95]
7. Accelerate the vehicle up to between 45 and
60 mph (70-100 km/h). This should take
approximately 5 minutes.
*
[SV51481( ALL)06/95]
8. Drive vehicle and hold the throttle steady at
the selected speed between 45 and 60 mph
(70-100 km/h) for approximately 5 minutes.
*
[SV51483( ALL)06/95]
9. Drive the vehicle for 5 minutes at varying
speeds between 45 and 60 mph
(70-100 km/h).
*
[SV51485( ALL)06/95]
10. Bring the vehicle back to idle. Idle in Drive
for 40 seconds.
*
[SV51487( ALL)06/95]
11. OBD II drive cycle has been completed.